What changes when a four-unit budget meets the full cost stack?
These figures demonstrate the arithmetic. They are invented inputs, not Burnaby market prices, municipal fee quotes, construction quotes or a statement that four units can be built.
Visible assumptions
| Input | Synthetic allowance |
|---|---|
| Revenue: 4 units × $1.2 million | $4,800,000 |
| Land | $1,600,000 |
| Acquisition costs | $50,000 |
| Demolition and site | $100,000 |
| Hard construction | $1,800,000 |
| Soft costs | $180,000 |
| Municipal and utility allowance | $120,000 |
| Financing and carry | $200,000 |
| Tax and other allowance | $50,000 |
| Contingency: 10% of hard costs | $180,000 |
| Selling: 3% of gross revenue | $144,000 |
The municipal allowance must be replaced with the actual applicable city schedules and project facts. Financing, tax, scope, sales timing and the construction budget require separate substantiation.
Reproduce the result
Gross revenue $4,800,000 − selling costs $144,000 − total project cost $4,280,000 = development profit $376,000.
Target profit is 15% of gross revenue: $720,000. Net revenue less non-land costs and target profit leaves a residual land budget of $1,256,000. Against the assumed land price, the difference is -$344,000.
This target-based land allowance is a scenario result, not a valuation.
Change the assumptions in the calculatorKeep downside visible
Lower sale proceeds, higher hard costs, longer carrying time, tax changes and a different permitted design can each change the result. The existing calculator exposes revenue and hard-cost stress; it does not model every schedule, debt, tax or absorption risk.
Before commissioning an economic scenario, establish which approval-pathway facts are supported by the record.